Fillmore High Athletic Complex Rises

Fillmore Unified School District Assistant Superintendent of Business Services Denise Berrington said, "Last week at the Fillmore High School Athletic Complex, crews poured the concrete for the gym floor and completed backfilling of the stormwater capture system. Temporary work platforms are being installed to allow crews to safely continue building the concrete block walls and prepare for the next concrete pour. This work helps support the structure as construction moves upward.

With deep underground utility work nearing completion, foundation and concrete slab work for the Lobby, Restrooms, Locker Rooms, Wrestling Rooms, Athletic Training Rooms, and Coaches’ Offices is scheduled to begin next week.

The anticipated construction completion date for the project is February 2027. We look forward to sharing continued progress as this exciting project takes shape!"